INSP-Final Inspection | 9/29/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Jim Page
|
|
|
Underground supply final inspection passed/complete.
|
INSP-Supply line flush | 12/22/2015 | 12/23/2015 | 12/23/2015 | A | DONE |
Jim Page
|
|
|
Main line underground flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2015 | 11/5/2015 | 11/5/2015 | A | PASS |
Jim Page
|
|
|
200 psi hydrostatic test passed/complete for underground piping.
|
INSP-Sprinkler Rough-in | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PART |
Thomas Walsh
|
|
|
Visual inspection of FS U/G from city conection to BOR stub up. Thrust block in place. U/G has not been hydrotested yet, so covering of pipe is at the contractor's risk.
|
Intake Approval | | | 5/7/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/7/2015 | | 5/7/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/7/2015 | | 5/7/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/7/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/7/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/7/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/7/2015 | | 5/7/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 5/6/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2015 5:03PM
|