INSP-Final Inspection | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 5/13/2015 | 5/14/2015 | 5/14/2015 | A | PART |
Troy Cobbley
|
|
|
The rough-in for the tenant space passed for the most part . Piping can be covered but additional upright protection is required around the room with no ceiling.
|
Sprinkler Plan Check | 5/13/2015 | | 5/13/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/13/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/13/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/13/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/13/2015 | | 5/13/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 5/12/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/12/2015 | | 5/12/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2015 8:09AM
|