Permit Information
Permit NumberFIR15-00319
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6687 W WINSTON LN
Project Name#6687 Aberdeen 4-Plex Phase 4
Customer Number 
ePlanReviewYes
Description
[Aberdeen 4-Plex Phase 4 #6687 - Building #3]
The fire sprinkler scope of work consists of protecting a four-plex with a NFPA 13R system

The underground was installed under permit FIR15-00310

L3B1 - 6687 Winston (Bldg 3): To construct a new 3,836 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms and two bathrooms. The 1st story units are 959 square feet and are required to be Type 'B' units. The 2nd story units are 959 square feet. All units share a common path of egress into and through a 1/2-hour rated exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00276 & CUP13-00017 Per Planning and Zoning. **SRZ*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/24/20157/24/20157/24/2015PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Supply line flush7/24/20157/24/20157/24/2015PCANC
DetailsTroy Cobbley
Wrong inspection type called in
INSP-Final Inspection7/21/20157/23/20157/23/2015AFAIL
DetailsTroy Cobbley
Flow switches failed to operate. Need soffits on exposed pipe in storage rooms
INSP-Sprinkler Rough-in6/5/20156/5/20156/5/2015PPASS
DetailsJim Page
Overhead sprinkler piping/tenting approved for cover
INSP-Supply line flush6/4/20156/5/20156/5/2015APASS
DetailsJim Page
Underground supply line flush complete
INSP-Sprinkler Rough-in6/3/20156/4/20156/4/2015ACANC
DetailsTroy Cobbley
Cancel per Colt Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro6/3/20156/3/20156/3/2015PPASS
DetailsTroy Cobbley
Above ground hydro test passed
INSP-Sprinkler Rough-in/Hydro6/1/20156/2/20156/2/2015PPASS
DetailsTroy Cobbley
Rough-in passed. No tenting installed yet.
Permit Ready to Issue  5/14/2015 DONE
all requirments met
Issue and Print Permit  5/14/2015 DONE
Inspection Record Card- Fire5/14/2015 5/14/2015 DONE
DetailsCarlos Velazquez
Intake Approval  5/13/2015 PASS
Plan assigned to (Tim)5/13/2015 5/13/2015 DONE
DetailsTim Frost
Sprinkler Plan Check5/13/2015 5/13/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  5/13/2015 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  5/13/2015 DONE
DetailsTim Frost
Application received  5/9/2015 DONE
Application submitted via PDS Online on May 9 2015 4:35PM