INSP-Final Inspection | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | PASS |
Jim Page
|
|
|
Final overhead fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2015 | 6/15/2015 | 6/15/2015 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for 1st level, 2nd level and FDC passed/complete
|
INSP-Sprinkler Rough-in | 6/10/2015 | 6/11/2015 | 6/11/2015 | P | PASS |
Jim Page
|
|
|
Overhead sprinkler piping/tenting approved for cover
|
INSP-Supply line flush | 6/9/2015 | 6/9/2015 | 6/10/2015 | P | CANC |
Jim Page
|
|
|
Canceled per converstaion with Colton, phone ####-####, service was not turned on to building.
|
INSP-Supply line flush | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | CANC |
Troy Cobbley
|
|
|
This is an underground flush request. Colton is the contact. Thanks! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Permit Ready to Issue | | | 5/14/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/14/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/14/2015 | | 5/14/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 5/13/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/13/2015 | | 5/13/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/13/2015 | | 5/13/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/13/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2015 4:37PM
|