INSP-Final Inspection | 8/4/2016 | 8/4/2016 | 8/4/2016 | A | PASS |
Jim Page
|
|
|
Final underground inspection passed/complete
|
INSP-Supply line flush | 8/3/2016 | 8/4/2016 | 8/4/2016 | A | DONE |
Jim Page
|
|
|
North main line flush completed after PIV relocation.
|
CHANGE STATUS TO (ISS) | | | 8/3/2016 | | DONE |
|
|
|
per Jim Page
|
INSP-Final Inspection | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Jim Page
|
|
|
Final underground fire sprinkler supply main inspection complete.
|
CHANGE STATUS TO (ISS) | | | 8/1/2016 | | DONE |
|
|
|
plan mod fees paid
|
Plan Modification Accepted | | | 8/1/2016 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 8/1/2016 | | 8/1/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/1/2016 | | 8/1/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/1/2016 | | DONE |
|
|
|
plan mod fees paid
|
CHANGE STATUS TO (ISS) | | | 8/1/2016 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2016 | 6/29/2016 | 6/29/2016 | A | PART |
Jim Page
|
|
|
Hydrostatic test for south side underground supply complete.
|
INSP-Supply line flush | 6/27/2016 | 6/29/2016 | 6/29/2016 | A | DONE |
Jim Page
|
|
|
South side underground supply main flushed
|
INSP-Supply line flush | 5/4/2016 | 5/6/2016 | 5/6/2016 | A | PASS |
Jim Page
|
|
|
Underfround flush for underground supply piping complete for both underground supplies.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test for underground supply piping passed/complete.
|
INSP-Sprinkler Rough-in | 4/22/2016 | 4/22/2016 | 4/22/2016 | P | PASS |
Jim Page
|
|
|
North post indicator valve relocated to line up with landscaping, Rough to cover inspection for relocation/thrust blocks complete, approved for cover.
|
INSP-Sprinkler Rough-in | 4/21/2016 | 4/21/2016 | 4/21/2016 | A | PART |
Jim Page
|
|
|
South supply main post indicator valve relocated to line up with tree location, underground inspection for relocation passed/complete. Relocation for north post indicator will be completed at later date.
|
INSP-Sprinkler Rough-in | 10/29/2015 | 10/29/2015 | 10/29/2015 | P | PART |
Thomas Walsh
|
|
|
Rough to cover inspection for fire service underground supply line (south side) for the convention center fire sprinkler systems. A portion of the supply line was sleeved as it passed through a foundation wall. NOTE: Supply line changed from permit set of plans, showing a change in layout - thrust blocks added for these changes as required. OK to cover pipe. NOTE: Contractor accepts the risk of burying pipe prior to hydrostatic test.
|
INSP-Supply line flush | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | FAIL |
Thomas Walsh
|
|
|
Rough inspection of fire service underground supply line (south side) into convention center portion of the building. U/G supply line penetrates building foundation without proper clearanace. Contractor agreed to remove pipe as needed to provide a clearance sleeve (10") around the 6" supply line.
|
INSP-Sprinkler Rough-in | 6/3/2015 | 6/3/2015 | 6/3/2015 | P | PART |
Jim Page
|
|
|
Two of the three stub-ins are ready for inspection. The two inspected at this time are the two stub-ins on the west side of the building, both west side stub-ins are approved for cover. The third stub-in still needs to be installed/ inspected before cover can be accomplished..
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/2/2015 | 6/3/2015 | P | CANC |
Jim Page
|
|
|
Spoke to the onsite point of contact for this inspection, Bryan Phone #: ###-####, the underground was not ready for inspection, verbally confirmed over the phone for inspection cancellation.
|
Intake Approval | | | 5/14/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/14/2015 | | 5/14/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/14/2015 | | 5/14/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/14/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/14/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/14/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/14/2015 | | 5/14/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 5/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 12 2015 9:44AM
|