Information based on query as of Monday, July 15, 2024.
Permit Information
Permit NumberFIR15-00356
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1125 W AMITY RD
Project NameNORCO WAREHOUSE EXPANSION
Customer Number 
ePlanReviewYes
Description
[Norco Warehouse Expansion]
The fire sprinkler scope of work consists of installing a new wet pipe system throughout the new warehouse expansion and canopy addition per NFPA 13 for ordinary hazard group II and high piled storage. Work will begin at new 6" connection to existing 6" riser and extend into the new warehouse. The new warehouse will be protected with ESFR type sprinklers. The dry system in the canopy will be fed from the existing dry canopy system.

To construct an 11,650 square foot, two story warehouse addition. 1st Floor: 8,750 sq. ft., 2nd Floor: 2,900 sq. ft.. This permit also includes the construction of a 1,315 square foot concrete dock, with metal roof cover that will connect two existing covered dock areas. The new dock cover and new warehouse addition will be separated by a two-hour fire wall separating the two buildings. There is an existing two-hour fire wall at the covered dock that will be relocated to line up with the new two-hour fire wall. This permit also includes related site improvements. The new warehouse will be constructed of a pre-engineered metal building (Behlen) with masonry exterior walls. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/8/20159/9/20159/9/2015APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
CHANGE STATUS TO (ISS)  9/8/2015 DONE
plan mod fees paid
Sprinkler Plan Check9/4/2015 9/4/2015 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  9/4/2015 DONE
DetailsTim Frost
INSP-Sprinkler Rough-in8/25/20158/26/20158/26/2015PPASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in/Hydro8/25/20158/25/20158/25/2015PPASS
DetailsTroy Cobbley
Overhead rough-in for the wet and dry systems passed. A plan modification is needed for the below mezzanine piping due to additional fittings on the main and an additional branchline. Overhead hydro tests passed on both the wet and dry systems. 24 hour air test started on the dry system with 47 psi on the guage at 3:00 pm.
Sprinkler Plan Check7/24/2015 7/24/2015 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/24/2015 DONE
DetailsTim Frost
(F) Reprint permit  7/24/2015 DONE
CHANGE STATUS TO (ISS)  7/24/2015 DONE
Sprinkler Plan Check7/22/2015 7/22/2015 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/22/2015 DONE
DetailsTim Frost
Permit Ready to Issue  7/22/2015 DONE
all requirments met
Issue and Print Permit  7/22/2015 DONE
Inspection Record Card- Fire7/22/2015 7/22/2015 DONE
DetailsCarlos Velazquez
Sprinkler Plan Check7/21/2015 7/21/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  7/21/2015 PASS
DetailsTim Frost
Plan assigned to (Tim)7/21/2015 7/21/2015 DONE
DetailsTim Frost
Miscellaneous action  7/21/2015 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  5/29/2015 PASS
Plan assigned to (Tim)5/29/2015 5/29/2015 DONE
DetailsTim Frost
Intake Approval  5/27/2015 FAIL
FP Contractor did not provide a description of what is being stored.
Application received  5/22/2015 DONE
Application submitted via PDS Online on May 22 2015 8:47AM