INSP-Final Inspection | 10/14/2015 | 10/15/2015 | 10/14/2015 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 7/20/2015 | 7/20/2015 | 7/20/2015 | P | PASS |
Jim Page
|
|
|
Inspected remaining area's associated with this permit, rough-in inspection passed/complete, all area's associated with this FIR approved for cover.
|
INSP-Final Inspection | 6/17/2015 | 6/17/2015 | 6/17/2015 | P | PART |
Jim Page
|
|
|
Notated areas that are finaled with red pen on the city approved drawings Still have other areas on the floor that needs to be rough in inspected as well as finaled.
|
INSP-Sprinkler Rough-in | 6/16/2015 | 6/16/2015 | 6/16/2015 | P | PART |
Jim Page
|
|
|
Notated area's approved for cover during this inspection in red on city approved plans. The second floor project is being split up to accomidate people, contractor will need to schedule rough to cover inspection for other area on 2nd floor.
|
Sprinkler Plan Check | 6/3/2015 | | 6/3/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/3/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/3/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/3/2015 | | 6/3/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 5/29/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/29/2015 | | 5/29/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/26/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 26 2015 11:14AM
|