Case Summary | | | 6/6/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 6/10/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need the tamper switch and alarm valve pressure switch in 380 tested and the the flow switch in 420 tested.
|
Telephone call | | | 6/4/2015 | | DONE |
|
|
|
Robert Gobler called to say that the fire alarm panel is to be moved from the riser room to a storage room approximately 30 feet to the west. He wanted to know if this would require a resubmittal. I informed him that since this does not affect any calculations that it could be done without resubmittal but would be require as built drawings at the completion of the project that indicate the change.
|
Permit Ready to Issue | | | 6/3/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 6/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/3/2015 | | 6/3/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Plan assigned to (Lee) | 6/2/2015 | | 6/2/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 6/2/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 6/2/2015 | | 6/2/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/2/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Application received | | | 6/1/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2015 3:05PM
|