INSP-Final Inspection | 3/22/2016 | 3/23/2016 | 3/23/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test, 2hrs @ 200psi passed/complete for overhead sprinkler piping.
|
Issue and Print Permit | | | 3/2/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 2/26/2016 | | 2/26/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/26/2016 | | DONE |
|
|
|
plans are in the fir drawer under M for Micron
|
Telephone call | | | 2/26/2016 | | DONE |
|
|
|
sent email to Paul that plan mod is ready
|
Plan assigned to (Tim) | 1/29/2016 | | 2/26/2016 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 2/18/2016 | | DONE |
|
|
|
resubmittals recieved 2 sheets #1, permit app, 1 cover sheet, 1 response letter, 2 hydraulic calcs-put in fire cubby
|
Plan assigned to (Troy) | 2/4/2016 | | 2/4/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/4/2016 | | 2/4/2016 | | FAIL |
Tim Frost
|
|
|
|
Plan Modification Accepted | | | 2/4/2016 | | DONE |
|
|
|
|
Telephone call | | | 2/4/2016 | | DONE |
|
|
|
emailed Paul that plan review failed and that he can come pick them up
|
INSP-Sprinkler Rough-in | 1/18/2016 | 1/19/2016 | 1/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
I stopped the rough-in inspection due to the installation not matching the approved plans. Branchlines have been added and several of the branchlines are not in the same location as the plans show them. It appears that the upright sprinkler heads have been hydraulically calculated and are shown placed directly on the branchlines. However they are actually installed on 1" armovers which changes the hydraulic calculations. I noted that there are additional fittings on the 4" main and the 2" branchlines. A low point drain will be needed as discussed. Plans will need to be resubmitted with all changes and revised hydraulic calculations.
|
Issue and Print Permit | | | 1/15/2016 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/10/2015 | | 1/13/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/13/2016 | | 1/13/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/13/2016 | | DONE |
|
|
|
|
Telephone call | | | 1/13/2016 | | DONE |
|
|
|
emailed Paul to let know the permit is ready
|
Plan resubmittals received | | | 1/11/2016 | | DONE |
|
|
|
received (2) sets of calculation & plans
|
Sprinkler Plan Check | 12/17/2015 | | 12/17/2015 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/17/2015 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 12/17/2015 | | DONE |
|
|
|
emailed Paul that the permit failed
|
Plan assigned to (Scott) | | | 6/11/2015 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 6/11/2015 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|