Case Summary | | | 12/8/2015 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/30/2015 | 10/1/2015 | 10/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/29/2015 | 9/30/2015 | 9/30/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need a print out of the signals sent and all of the duct smoke detectors tested (could not put hvac units in heat mode today) All other devices tested ok.
|
CHANGE STATUS TO (ISS) | | | 8/10/2015 | | DONE |
Christina Prado
|
|
|
|
Alarm Plan Check | 8/4/2015 | | 8/4/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/4/2015 | | DONE |
|
|
|
Plan mod approved with new review comments.
|
Plan resubmittals received | | | 8/3/2015 | | DONE |
|
|
|
Plan modification received that adds 4 duct smoke detectors.
|
Miscellaneous action | | | 7/30/2015 | | DONE |
|
|
|
Rob Ahten requested projectdox reopened to submit a plan mod for added duct smoke detectors.
|
Permit Ready to Issue | | | 6/17/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 6/17/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/17/2015 | | 6/17/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Plan assigned to (Lee) | 6/16/2015 | | 6/16/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 6/16/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 6/16/2015 | | 6/16/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/16/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Application received | | | 6/15/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 15 2015 11:19AM
|