INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Jim Page
|
|
|
Final alarm/actuation test passed/complete
|
1st review completed | | | 6/18/2015 | | PASS |
|
|
|
|
Sprinkler Plan Check | 6/18/2015 | | 6/18/2015 | | PASS |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 6/18/2015 | | 6/18/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/18/2015 | | DONE |
|
|
|
Plans approved with review comments and drawing notation. Projectdox updated.
|
Permit Ready to Issue | | | 6/18/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/18/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/18/2015 | | 6/18/2015 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 6/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 17 2015 5:42AM
|
Plan assigned to (Lee) | 6/17/2015 | | 6/17/2015 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 6/17/2015 | | DONE |
|
|
|
Fire alarm review complete. Sent to Tim Frost for sprinkler review.
|
Miscellaneous action | | | 6/17/2015 | | DONE |
|
|
|
Email to Clark Mackay to clarify if hot area of racks has a hard lid or is open to the suspended ceiling. He responded to indicate the hot area has a plexiglass type of ceiling. I informe him that since an FM200 nozzle was located in this room that 2 of the detectors would need to be there as well.
|