INSP-Final Inspection | 8/10/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Katie Marron
|
|
|
Scope of work complete. Permit finaled.
|
INSP-Final Inspection | 8/5/2015 | 8/6/2015 | 8/7/2015 | A | CANC |
Troy Cobbley
|
|
|
Need ceiling tile for a final
|
INSP-Sprinkler Rough-in | 8/5/2015 | 8/6/2015 | 8/6/2015 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
Issue and Print Permit | | | 7/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/30/2015 | | 7/30/2015 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 7/15/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 7/15/2015 | | 7/15/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/15/2015 | | 7/15/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/15/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/15/2015 | | DONE |
|
|
|
all requirments met
|
Application received | | | 7/6/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 6 2015 4:52PM
|