INSP-Sprinkler Rough-in/Hydro | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | CANC |
Jim Page
|
|
|
Cancelled by contractor when contacted, valve leaking by on city side, contractor will reshedule inspection after repair is made.
|
INSP-Sprinkler Rough-in | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | PASS |
Jim Page
|
|
|
Underground piping approved for cover
|
Intake Approval | | | 7/10/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 7/10/2015 | | 7/10/2015 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 7/10/2015 | | DONE |
|
|
|
Contactor calles and asked that this permit be treated as a quick permit
|
Sprinkler Plan Check | 7/10/2015 | | 7/10/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/10/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/10/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 7/10/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/10/2015 | | 7/10/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 7/9/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 9 2015 3:20PM
|