INSP-Final Inspection | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | CANC |
Jim Page
|
|
|
Spoke to Brian with Absolute, inspection will be rescheduled for 08DEC2015.
|
INSP-Sprinkler Rough-in | 11/13/2015 | 11/13/2015 | 11/13/2015 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection passed/complete for 2nd floor, entire floor approved for cover.
|
INSP-Sprinkler Rough-in | 11/5/2015 | 11/9/2015 | 11/9/2015 | A | PART |
Jim Page
|
|
|
Rough to cover inspection passed/complete for basement level work, first floor work and exterior office spaces on 2nd floor. These mentioned area's approved for cover. Contractor will schedule rough to cover for remaining area's of 2nd floor when complete.
|
Intake Approval | | | 7/20/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 7/20/2015 | | 7/20/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/20/2015 | | 7/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/20/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/20/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/20/2015 | | 7/20/2015 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 7/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2015 9:07AM
|