Permit Information
Permit NumberFIR15-00503
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 420 S ORCHARD ST
Project NameTHE VILLAGE CHARTER SCHOOL
Customer Number 
ePlanReviewYes
Description
[The Village Charter School]
The fire sprinkler scope of work consists of school. New 4” C-900 underground will supply a 4” backflow preventer and 4” riser. The side feed system utilizes extended coverage sprinklers.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

The tenant project will involve two new interior framed walls, doors and finishes, modification of the existing suspended ceiling, lights and mechanical system in classroom 109a and 110.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/24/20158/24/20158/24/2015PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro8/22/20158/22/20158/22/2015PPASS
DetailsThomas Walsh
Hydrotest of FS U/G supply line from city connection to A/S BOR - 200 psi @ hours - PASSED. Waterflow device tested OK
Contractor still in process of sheet rocking areas where sprinklers protrude through ceiling. Also need to install ceiling in electrical closet. Need to install 4-way siesmic brace at top of riser.
Will inspect these discrepancies at final inspection.
INSP-Sprinkler Rough-in/Hydro8/21/20158/21/20158/21/2015PPART
DetailsThomas Walsh
Flush test of FS U/G supply line from city connection to A/S BOR (before connection to A/S system.
Flushed clear after 2 attempts. OK to connect to A/S BOR.
INSP-Supply line flush8/20/20158/21/20158/21/2015PPART
DetailsThomas Walsh
Witnessed hydrostatic test of above ground system (200 psi @ 2 ours) - PASSED
NOTE: FS U/G supply line installed but not hydrotested yet - scheduled for tomorrow 8/22. Following hydro and flush, connection to A/G system will be made and the system put into service.
INSP-Sprinkler Rough-in/Hydro8/20/20158/21/20158/21/2015APART
DetailsThomas Walsh
Started hydrotest @ 1045 - 200 psi. Rough inspection conducted 8/20.
INSP-Sprinkler Rough-in8/19/20158/20/20158/20/2015APASS
DetailsTroy Cobbley
The overhead rough-in passed and piping can be covered except at the wall where the insulation needs to be installed in the stud bays and at the locations for the missing branch line restraints. No riser has been installed/built. Underground supply has not been connected at the street yet.
INSP-Sprinkler Rough-in8/17/20158/18/20158/18/2015APASS
DetailsTroy Cobbley
The remaining underground has been installed by tunneling. I need documentation verifying that the minimum 4'6" bury depth has been met. I was able to verify depth at the point of connection to tvfp piping.
INSP-Sprinkler Rough-in8/11/20158/12/20158/12/2015APASS
DetailsTroy Cobbley
Underground supply stub out only ok to cover.
Sprinkler Plan Check7/29/2015 7/29/2015 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/29/2015 DONE
DetailsTim Frost
Permit Ready to Issue  7/29/2015 DONE
Issue and Print Permit  7/29/2015 DONE
Inspection Record Card- Fire7/29/2015 7/29/2015 DONE
DetailsBrittany Hill
Sprinkler Plan Check7/23/2015 7/23/2015 FAIL
DetailsTim Frost
1st review completed  7/23/2015 FAIL
DetailsTim Frost
Application received  7/22/2015 DONE
Application submitted via PDS Online on Jul 22 2015 10:02AM
Intake Approval  7/22/2015 PASS
Plan assigned to (Tim)7/22/2015 7/22/2015 DONE
DetailsTim Frost