Case Summary | | | 12/9/2015 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. system is on line
|
INSP-Final Inspection | 8/24/2015 | 8/25/2015 | 8/24/2015 | A | PASS |
Scott Arellano
|
|
|
Passed
|
INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | P | PART |
Thomas Walsh
|
|
|
Fire alarm system test for a new charter school. Tested all initiating devices, including SDs, DDs, MP,s tamper, etc, and notification throughout the building. All devices tested OK. Offsite monitoring confimed, however system will not be put into service until the fire sprinkler system is ready to be put into service.
|
Plan resubmittals received | | | 8/14/2015 | | DONE |
|
|
|
Resubmittal to show revised floor plans.
|
Alarm Plan Check | 8/14/2015 | | 8/14/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/14/2015 | | DONE |
|
|
|
Plan modification resubmittal approved with new review comments.
|
CHANGE STATUS TO (ISS) | | | 8/14/2015 | | DONE |
|
|
|
plan modification passed & paid for
|
Permit Ready to Issue | | | 8/11/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/11/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/11/2015 | | 8/11/2015 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 8/10/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 8/10/2015 | | 8/10/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/10/2015 | | DONE |
|
|
|
Plans approved as noted with review comments.
|
Plan assigned to (Lee) | 8/7/2015 | | 8/7/2015 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 8/7/2015 | | DONE |
|
|
|
Fire alarm plans do not appear to be the same as bldg. permit plans. Emailed Neal Timmerman to confirm his drawings are correct. Neal responded to indicate the fire alarm plans were right.
|
Application received | | | 8/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 5 2015 10:47PM
|