INSP-Final Inspection | 10/28/2015 | 10/28/2015 | 10/28/2015 | P | PASS |
Jim Page
|
|
|
Final underground fire sprinkler supply inspection passed/complete
|
INSP-Supply line flush | 10/26/2015 | 10/28/2015 | 10/28/2015 | A | DONE |
Jim Page
|
|
|
Main underground supply line flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic test pased/complete
|
INSP-Sprinkler Rough-in | 9/4/2015 | 9/4/2015 | 9/4/2015 | P | PASS |
Jim Page
|
|
|
Underground inspection passed/complete, approved for cover
|
INSP-Sprinkler Rough-in | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PART |
Jim Page
|
|
|
Partial cover for fire main installed, the rest of the underground fire main will be installed at later date.
|
Intake Approval | | | 8/11/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/11/2015 | | 8/11/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/11/2015 | | 8/11/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/11/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/11/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/11/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/11/2015 | | 8/11/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 8/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2015 10:03AM
|