INSP-Final Inspection | 10/3/2016 | 10/3/2016 | 10/3/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Final Inspection | 9/29/2016 | 9/30/2016 | 9/30/2016 | P | CANC |
Jim Page
|
|
|
Final fire sprinkler inspection will be rescheduled to coincide with tamper switch wiring completion , tamper switches on backflow and fire pump control valve were not in place. Tamper switches were installed while alarm inspection was happening but still need to be wired into the alarm system.
|
INSP-Sprinkler Rough-in | 9/13/2016 | 9/20/2016 | 9/20/2016 | P | DONE |
Jim Page
|
|
|
Fire pump start up complete.
|
INSP-Sprinkler Rough-in | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 4 complete, overhead fire sprinkler piping located on level 4 approved for cover. Rough to cover inspection complete for overhead fire sprinkler piping located above the hardlids on level 1, overhead fire sprinkler piping located above the hardlids on level 1 approved for cover
|
INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | CANC |
Jim Page
|
|
|
Rough to cover inspection cancelled by point of contact, Mark Jensen ( ###-#### ), rough to cover inspection will be rescheduled for a later date.
|
INSP-Sprinkler Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 4 complete, overhead fire sprinkler piping located on level 4 approved for cover. Rough to cover inspection complete for overhead fire sprinkler piping located above the hardlids on level 1, overhead fire sprinkler piping located above the hardlids on level 1 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/6/2016 | 7/7/2016 | 7/7/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping located on levels 2 and 3, overhead fire sprinkler piping on levels 2 and 3 approved for cover.
|
INSP-Sprinkler Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for hardlids located in the 4th floor stairwell, notated the city approved drawings with yellow highlighter the lines that were inspected. Area's notated with yellow highlighter approved for cover.
|
INSP-Sprinkler Rough-in | 5/3/2016 | 5/5/2016 | 5/5/2016 | P | PART |
Jim Page
|
|
|
Notated area's inspected with green highlighter on city approved plans. Area's notated approved for cover.
|
INSP-Sprinkler Rough-in | 3/31/2016 | 4/1/2016 | 4/1/2016 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled, discussed reschedule with point of contact, Mark, phone number ###-####. Rough in inspection will be rescheduled for 04APR16.
|
INSP-Sprinkler Rough-in | 3/16/2016 | 3/16/2016 | 3/16/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for elevator equipment on 1st floor complete, elevator equipment room fire sprinkler piping approved for cover. Notated area for cover with red ink on city approved drawings.
|
Miscellaneous action | | | 10/26/2015 | | DONE |
|
|
|
Email regarding space above stair tower.
Tom,
Per our conversations.
I believe the space at the top of the stair tower meets the intent of the code section below. The space above the stair tower can only be accessed when you climb the far stair tower, go across the roof and enter this space.
A sign shall be provided on the door, indicating the space cannot be occupied or be used for any type of storage. The space shall remain locked at all times. If at a later date the space is found to be in use, fire protection will immediately required.
8.15.1.2.1* Concealed spaces of noncombustible and limited combustible construction with minimal combustible loading
having no access shall not require sprinkler protection.
|
Permit Ready to Issue | | | 10/15/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/15/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/15/2015 | | 10/15/2015 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 10/12/2015 | | 10/12/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/9/2015 | | 10/9/2015 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/30/2015 | | 9/30/2015 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/26/2015 | | 8/26/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/26/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/26/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 8/25/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/25/2015 | | 8/25/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/10/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 10 2015 11:11AM
|