INSP-Final Inspection | 1/26/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/7/2016 | 1/11/2016 | 1/11/2016 | A | FAIL |
Troy Cobbley
|
|
|
Will be ok to final when the plastice barrier has been removed from the Game Store location.
|
INSP-Sprinkler Rough-in | 1/7/2016 | 1/11/2016 | 1/11/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed
|
INSP-Sprinkler Rough-in | 1/7/2016 | 1/11/2016 | 1/7/2016 | A | CANC |
Troy Cobbley
|
|
|
We want to coordinate the rough-ins and finals for Permits FIR15-00263 and FIR15-00570 to all happen at the same time, since they are both part of Overland Park Plaza. Please contact Gordon Rogers (his phone # is given) at least a half hour prior to arrival so that he can have time to make it there himself. Phone #: ###-#### >> Inspection requested via web by Connie Danes Inspection cancelled from web by: Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 1/7/2016 | 1/11/2016 | 1/7/2016 | A | CANC |
Troy Cobbley
|
|
|
We want to coordinate the rough-ins and finals for Permits FIR15-00263 and FIR15-00570 to all happen at the same time, since they are both part of Overland Park Plaza. Please contact Gordon Rogers (his phone # is given) at least a half hour prior to arrival so that he can have time to make it there himself. Thanks! Phone #: ###-#### >> Inspection requested via web by Connie Danes Inspection cancelled from web by: Connie Danes
|
INSP-Sprinkler Rough-in | 9/22/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Troy Cobbley
|
|
|
See my marked ups on plan sheet FP3 and FP4 for areas inspected. No insulation of the attic space or provisions for heat have been provided at this point.
|
Permit Ready to Issue | | | 8/24/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/24/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/24/2015 | | 8/24/2015 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 8/20/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/20/2015 | | 8/20/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/20/2015 | | 8/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/20/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/13/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2015 1:12PM
|