INSP-Final Inspection | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 2/12/2016 | 2/12/2016 | 2/12/2016 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. painted heads changed out. Piping can be covered.
|
INSP-Sprinkler Rough-in | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | PART |
Troy Cobbley
|
|
|
Overhead rough-in passed but the piping can not be covered because many of the upright sprinkler heads have been painted. When they have been changed out a re-inspection will be needed for cover.
|
Sprinkler Plan Check | 8/21/2015 | | 8/21/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/21/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/21/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/21/2015 | | 8/21/2015 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 8/20/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/20/2015 | | 8/20/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2015 1:55PM
|