INSP-Final Inspection | 3/7/2016 | 3/8/2016 | 3/7/2016 | A | CANC |
Jim Page
|
|
|
Don Phone #: ###-####
|
INSP-Final Inspection | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PASS |
Jim Page
|
|
|
Final underground fire sprinkler final passed/complete
|
INSP-Supply line flush | 2/25/2016 | 2/25/2016 | 2/25/2016 | P | DONE |
Jim Page
|
|
|
Undergrund main supply flush complete.
|
INSP-Sprinkler Rough-in | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | PASS |
Katie Marron
|
|
|
Underground supply ok to cover.
|
Permit Ready to Issue | | | 8/21/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 8/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/21/2015 | | 8/21/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 8/20/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/20/2015 | | 8/20/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/20/2015 | | 8/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/20/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 18 2015 7:22PM
|