Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR15-00604
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 650 N MILWAUKEE ST
Project NameCAFE ZUPAS T.I.
Customer Number 
ePlanReviewYes
Description
[Café Zupas TI.]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

(CAFE ZUPAS) Permit for tenant improvements to an existing 7,117 sq. ft. building originally constructed for TGI Fridays restaurant by separating the new 3,301 sq. ft. vacant tenant space under BLD15-02309 and creating a new 3,816 sq. ft. Cafe Zupas restaurant. Approval contingent upon adhering to the approved plans on file. Work to include the construction of a new nonbearing 1 hour rated demising wall, removal of some exterior brick veneer and exterior wall to accommodate a new storefront system, construction of new interior nonbearing walls to create ADA restrooms, server room, kitchen area, serving area and condiment bar area, relocation of electrical panels, new lighting fixtures, removal of existing RTUs addition of new RTUs and exhaust fans, new mechanical ductwork, new millwork and counters and interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/9/201510/9/201510/9/2015APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in10/2/201510/2/201510/2/2015PPASS
DetailsTroy Cobbley
IT room sprinkler piping is ok to cover
INSP-Sprinkler Rough-in/Hydro9/24/20159/24/20159/24/2015PPASS
DetailsTroy Cobbley
Piping above the gridded ceilings is ok to cover.
INSP-Sprinkler Rough-in/Hydro8/28/20158/28/20158/28/2015PPASS
DetailsTroy Cobbley
See the city approved plans for locations where the hardlids can be installed to cover piping.
Intake Approval  8/27/2015 PASS
Plan assigned to (Tim)8/27/2015 8/27/2015 DONE
DetailsTim Frost
Sprinkler Plan Check8/27/2015 8/27/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  8/27/2015 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  8/27/2015 DONE
DetailsTim Frost
Permit Ready to Issue  8/27/2015 DONE
Issue and Print Permit  8/27/2015 DONE
Inspection Record Card- Fire8/27/2015 8/27/2015 DONE
DetailsCandy A. Nichols
Application received  8/26/2015 DONE
Application submitted via PDS Online on Aug 26 2015 12:25PM