Permit Information
Permit NumberFIR15-00610
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 139 S BROADWAY AVE
Project NameBROADWAY SHOPS SOUTH BUILING
Customer Number 
ePlanReviewYes
Description
[Broadway Shops South Building]
The fire sprinkler scope of work consists of protecting a shell with a wet system. The building has a demising wall towards the middle, the building is higher on one side of the demising than the other.The system is design as two side feed system. The system is supplied by 6”x165’± C-900 underground with associate fittings and thrust blocks. The 6”riser has a 6” backflow preventer with a wall PIV. The two cross-mains are 3”. The feed main is 3” and the branch line are 2”

(139 BROADWAY – Shell and Core – South Bldg.) Permit is to remodel an existing 6,249 square foot building. Remodel consists of a complete exterior façade remodel including new soffits and storefront. Scope of work includes: interior demolition, new mechanical, new plumbing, new electrical, installation of a new sprinkler system, exterior soffits, new storefronts, remodel one restroom to become fully accessible (the other restrooms will be remodeled with tenant improvements), and interior finishes. At the competition of this project the building will be Fully Fire Sprinklered. NOTE: Separate Building Permits are required prior to occupying this space. No tenant improvement permits will be issued until non-build agreement is recorded and approved by the City of Boise Legal Dept. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/19/201511/20/201511/20/2015APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in/Hydro10/29/201510/29/201510/29/2015PPASS
DetailsJim Page
200 psi hydrostatic test passed/complete for overhead fire sprinkler piping.
INSP-Sprinkler Rough-in10/7/201510/7/201510/7/2015PPASS
DetailsJim Page
Fire sprinkler Rough in inspection passed/complete
Permit Ready to Issue  9/9/2015 DONE
Issue and Print Permit  9/9/2015 DONE
Inspection Record Card- Fire9/9/2015 9/9/2015 DONE
DetailsChristina Prado
Intake Approval  9/8/2015 PASS
Plan assigned to (Tim)9/8/2015 9/8/2015 DONE
DetailsTim Frost
Sprinkler Plan Check9/8/2015 9/8/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  9/8/2015 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  9/8/2015 DONE
DetailsTim Frost
Application received  8/28/2015 DONE
Application submitted via PDS Online on Aug 28 2015 10:24AM