INSP-Final Inspection | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2015 | 10/1/2015 | 10/1/2015 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection passed/complete, approved for cover
|
Intake Approval | | | 9/25/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 9/25/2015 | | 9/25/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/25/2015 | | 9/25/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/25/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/25/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/25/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/25/2015 | | 9/25/2015 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 9/22/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2015 3:19PM
|