INSP-Final Inspection | 4/13/2016 | 4/15/2016 | 4/15/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | CANC |
Troy Cobbley
|
|
|
OH Hydro Passed
|
INSP-Sprinkler Rough-in | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for pendant heads marked "ok" where piping can be covered in the lower ceilings in the first floor east end rooms.
|
INSP-Sprinkler Rough-in | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Katie Marron
|
|
|
Soffit heads in 7 rooms on 2nd floor "ok", plans marked accordingly.
|
INSP-Sprinkler Rough-in | 1/15/2016 | 1/15/2016 | 1/15/2016 | P | PASS |
Jim Page
|
|
|
Notated area's with red ink on the city approved drawings inspected for rough to cover, area's notated approved for cover
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/6/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection performed for phase 3, notated with red ink on the city approved drawings that are okay to cover.
|
INSP-Sprinkler Rough-in | 12/30/2015 | 12/31/2015 | 12/31/2015 | A | PART |
Katie Marron
|
|
|
Phase 2 Rough to cover ok at the following areas and as marked on the job site plans: -Second floor all Phase 2 rooms and corridors EXCEPT Common Rooms -First room all Phase 2 rooms EXCEPT dry sidewall over porches.
Still to be inspected are the first floor corridors, common areas and elevator area
|
INSP-Sprinkler Rough-in | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | CANC |
Katie Marron
|
|
|
Phase 2 RTC Please call Ricky 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 12/23/2015 | 12/23/2015 | 12/23/2015 | P | PART |
Katie Marron
|
|
|
2nd Floor Two more rooms marked "ok" on the plans where rough-in and tenting is passed and the piping can be covered. Verified previous inspection notice of dry sidewalls have been installed all four rooms on 2nd flr inspected so far.
|
INSP-Sprinkler Rough-in | 12/21/2015 | 12/22/2015 | 12/22/2015 | A | PART |
Troy Cobbley
|
|
|
2nd Floor has two rooms marked "ok" on the plans where the rough-in and tenting is passed and the piping can be covered. Except the piping for the balcony sidewalls has not been installed. This piping will need to be inspected prior to covering.
|
INSP-Sprinkler Rough-in | 12/11/2015 | 12/14/2015 | 12/14/2015 | A | PASS |
Troy Cobbley
|
|
|
RTC - OH 1st floor - Phase 1 See the city approved plans for the branchlines marked "ok" where piping rough-in passed. Need another inspection to verify the 3 1/2" of insulation installed in the joist channels.
|
INSP-Sprinkler Rough-in | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was just for the first floor corridor riser nipples and the short lenght of 1" piping from the riser nipples to the corridor walls. Contractor needs to cover this piping which is approved to do so. See the city approved plans for piping circled in red.
|
Sprinkler Plan Check | 10/14/2015 | | 10/14/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/14/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/14/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/14/2015 | | 10/14/2015 | | DONE |
Brittany Hill
|
|
|
|
Miscellaneous action | | | 10/13/2015 | | DONE |
|
|
|
Emailed contractor asking for Hyd Cover Sht. Project is ready to be approved after they are receieved and reviewed.
|
Sprinkler Plan Check | 10/7/2015 | | 10/7/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/7/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
1st review completed | | | 10/2/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/2/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 10/2/2015 | | 10/2/2015 | | FAIL |
Tim Frost
|
|
|
|
Intake Approval | | | 10/1/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/1/2015 | | 10/1/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 9/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 29 2015 3:22PM
|