INSP-Final Inspection | 12/5/2016 | 12/6/2016 | 12/6/2016 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection passed/complete
|
INSP-Supply line flush | 11/29/2016 | 11/30/2016 | 11/30/2016 | P | DONE |
Katie Marron
|
|
|
Supply line flush completed.
|
INSP-Supply line flush | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | CANC |
Scott Arellano
|
|
|
Suez Water is scheduled to do the flush at 1pm. Please call Jake if there is a conflict. This flush is for building P underground, overhead permit #FIR16-00266. Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/8/2016 | 7/8/2016 | 7/8/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply for building P complete, underground for building P approved for cover. Building P still needs hydrostatic test and flush completed on underground supply.
|
INSP-Supply line flush | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | DONE |
Jim Page
|
|
|
Underground flushes for buildings T & O complete. Building P still needs underground rough to cover inspection, hydro and flush completed.
|
INSP-Supply line flush | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Jim Page
|
|
|
Underground Hydro test complete for buildings T and O. Buildings T and O rough to cover inspection complete for underground supply, nderground for T and O approved for cover.
|
Permit Ready to Issue | | | 10/20/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/20/2015 | | 10/20/2015 | | DONE |
Brittany Hill
|
|
|
|
(F) Reprint permit | | | 10/20/2015 | | DONE |
|
|
|
|
Intake Approval | | | 10/5/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/5/2015 | | 10/5/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/5/2015 | | 10/5/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/5/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/1/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 1 2015 11:04AM
|