Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR15-00689
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7466 W SAXTON DR
Project NameKensington Apartment Community
Customer NumberUDG ONLY
ePlanReviewYes
Description
Underground fire service lines for Buildings T, O & P

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

There does not seem to be an associated building permit at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/5/201612/6/201612/6/2016PPASS
DetailsJim Page
Final underground supply inspection passed/complete
INSP-Supply line flush11/29/201611/30/201611/30/2016PDONE
DetailsKatie Marron
Supply line flush completed.
INSP-Supply line flush11/28/201611/29/201611/29/2016PCANC
DetailsScott Arellano
Suez Water is scheduled to do the flush at 1pm. Please call Jake if there is a conflict. This flush is for building P underground, overhead permit #FIR16-00266. Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in7/8/20167/8/20167/8/2016PPASS
DetailsJim Page
Rough to cover inspection for underground supply for building P complete, underground for building P approved for cover. Building P still needs hydrostatic test and flush completed on underground supply.
INSP-Supply line flush4/6/20164/6/20164/6/2016PDONE
DetailsJim Page
Underground flushes for buildings T & O complete. Building P still needs underground rough to cover inspection, hydro and flush completed.
INSP-Supply line flush3/11/20163/11/20163/11/2016PPASS
DetailsJim Page
Underground Hydro test complete for buildings T and O. Buildings T and O rough to cover inspection complete for underground supply, nderground for T and O approved for cover.
Permit Ready to Issue  10/20/2015 DONE
Issue and Print Permit  10/20/2015 DONE
Inspection Record Card- Fire10/20/2015 10/20/2015 DONE
DetailsBrittany Hill
(F) Reprint permit  10/20/2015 DONE
Intake Approval  10/5/2015 PASS
Plan assigned to (Tim)10/5/2015 10/5/2015 DONE
DetailsTim Frost
Sprinkler Plan Check10/5/2015 10/5/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  10/5/2015 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  10/5/2015 DONE
DetailsTim Frost
Application received  10/1/2015 DONE
Application submitted via PDS Online on Oct 1 2015 11:04AM