Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR15-00695
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 896 N MAPLE GROVE RD
Project Name#896 Ashville Commons 4-Plex
Customer Number 
ePlanReviewYes
Description
[Ashville Commons 4-Plex - #896]
The fire sprinkler scope of work consists of CPVC piping is being used with extended coverage residential sprinklers to protect a two level, four unit apartment building using NFPA 13R

The underground piping is under permit FIR15-00533

(13 PERMITS UNDER CASE BLD15-00237 in ePlanReview) Bldg A (1) - Type 3 (Elev 3, A-203): To construct a new 3,804 sq. ft., two story, Four unit, apartment building. Each unit has two bedrooms, two bathrooms, and 951 square feet. The 1st story units are required to be Type 'B' units. All units share a common path of egress into and through a 1/2-hour rated exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00300 & PUD12-00012 Per Planning and Zoning. **SRZ*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/23/201512/24/201512/24/2015APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Sprinkler Rough-in10/23/201510/23/201510/23/2015PPASS
DetailsJim Page
Rough to cover inspection for overhead piping passed/complete, overhead fire sprinkler pipe tenting passed/complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro10/19/201510/20/201510/20/2015APASS
DetailsTroy Cobbley
Overhead hydro test passed.
INSP-Sprinkler Rough-in10/19/201510/20/201510/20/2015APASS
DetailsTroy Cobbley
Rough-in passed. Piping can not be covered until a tenting inspection has passed.
Permit Ready to Issue  10/7/2015 DONE
Issue and Print Permit  10/7/2015 DONE
Inspection Record Card- Fire10/7/2015 10/7/2015 DONE
DetailsChristina Prado
Intake Approval  10/6/2015 PASS
Sprinkler Plan Check10/6/2015 10/6/2015 DONE
DetailsTim Frost
Sprinkler Plan Check10/6/2015 10/6/2015 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  10/6/2015 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  10/6/2015 DONE
DetailsTim Frost
Application received  10/5/2015 DONE
Application submitted via PDS Online on Oct 5 2015 2:09PM