INSP-Final Inspection | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is ok for life safety with Scott's permission. I need as-builts, replace head in Room 105 and the exposed plastic pipe in the east stair well corrected.
|
Plan resubmittals received | | | 8/9/2016 | | PASS |
|
|
|
As Built
|
Plan assigned to (Tim) | 8/9/2016 | | 8/9/2016 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/9/2016 | | DONE |
|
|
|
as per Tim Frost-no fees due for the as built
|
INSP-Final Inspection | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | FAIL |
Troy Cobbley
|
|
|
Need outside alarm bell installed and tested, need flow switches tested, need as-builts, need damaged heads replaced and missing canopies and ceiling tile installed. Need revised floor plan/wall layout for laundry area.
|
INSP-Final Inspection | 8/4/2016 | 8/5/2016 | 8/5/2016 | P | FAIL |
Troy Cobbley
|
|
|
Due to problems on the fire alarm system todays inspection was a walk through of the 4th and 3rd floors. I noted the need for as-builts due to pipe routing changes at the stairwells and the added heads beneath the first floor tilt up doors. Contractor did not have any approved drawings or small documents except for the revised first floor plans.
|
INSP-Final Inspection | 8/3/2016 | 8/4/2016 | 8/4/2016 | P | CANC |
Troy Cobbley
|
|
|
Richard Clark is the contact on the inspection. Richard would like a final inspection on 8/4/16 PM. Thank you Phone #: ###-#### Inspection requested via web by Kay Haney
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PASS |
Troy Cobbley
|
|
|
Please schedule the inspection Overhead hydro's for 1st, 2nd, and 3rd floors passed.
|
INSP-Sprinkler Rough-in | 7/12/2016 | 7/13/2016 | 7/13/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location of pendant sprinkler heads that are ok to cover today. Conference room/adjoining room.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2016 | 7/8/2016 | 7/8/2016 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Ben
|
INSP-Sprinkler Rough-in/Hydro | 7/5/2016 | 7/6/2016 | 7/6/2016 | A | PART |
Troy Cobbley
|
|
|
4th floor hydro test passed. 3rd, 2nd and the standpipes failed due to visible loss on guages.
|
Plan Modification Accepted | | | 7/5/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/5/2016 | | 7/5/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/5/2016 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Troy Cobbley
|
|
|
The piping above the second and third floor hardlid at the west stairs is ok to cover and the second floor elevator lobby piping is ok to cover.
|
INSP-Sprinkler Rough-in | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PART |
Troy Cobbley
|
|
|
2nd floor rough to cover inspection for the hardlids in the corridor passed except for the very west end in front of the stairs where a pendant head is missing.
|
Plan Modification Accepted | | | 5/31/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/31/2016 | | 5/31/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/31/2016 | | DONE |
|
|
|
|
INSP-Conference | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | DONE |
Troy Cobbley
|
|
|
Mike and I spoke about fire rated assemblies and I deferred him to the building inspector
|
Miscellaneous action | | | 5/25/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
INSP-Sprinkler Rough-in | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for level 3 corridor soffits, level 3 corridor soffits approved for cover.
|
INSP-Sprinkler Rough-in | 5/4/2016 | 5/5/2016 | 5/5/2016 | P | PASS |
Troy Cobbley
|
|
|
The rough to cover inspection for the main corridor/soffits of the 4th floor passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 4/25/2016 | 4/26/2016 | 4/26/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping on 1st and 2nd floor hardlids, 1st and 2nd floor hardlids approved for cover.
|
INSP-Sprinkler Rough-in | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough to cover 3rd and 4th floor passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 4/7/2016 | 4/8/2016 | 4/8/2016 | A | PASS |
Troy Cobbley
|
|
|
3rd and 4th floor Rooms inspection passed. Piping above rooms and in stairwells can be covered. Corridor piping is not complete yet.
|
INSP-Sprinkler Rough-in | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | DONE |
Troy Cobbley
|
|
|
Today was more of a conference. Robert and I discussed earth quake bracing attachment for the stand pipes. He also relocated the pendant in the Roof Access room for better coverage.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2016 | 4/5/2016 | 4/5/2016 | A | PASS |
Troy Cobbley
|
|
|
4th floor and 3rd floor piping above Resident Rooms is ok to cover. Hall way piping is not complete and can not be covered. Robert and I spoke about two rooms on each floor where the sidewall heads are overspaced. This issue is to be addressed prior to cover either through new heads/piping or a change in sidewall heads. Either direction taken will need to be approved prior to cover.
|
INSP-Sprinkler Rough-in | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | CANC |
Troy Cobbley
|
|
|
4th floor insulation was not ready til late in the afternoon when I was not available for the inspection. I rescheduled for tomorrow morning early.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was just for cover on the 4th floor rooms. Rough-in for the rooms only passed but can't be covered yet since it appears that the concealed space is to be filled with insulation. If so I will need to verify that the insulation has been installed above the piping like a typical tenting inspection. At that point an approval for cover can be given.
|
INSP-Sprinkler Rough-in | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | PASS |
Troy Cobbley
|
|
|
The first floor main corridor pipe hanger attachment points are ok to cover. The is for the 2 1/2" main and 6" main.
|
Sprinkler Plan Check | 11/25/2015 | | 11/25/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/25/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/25/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/25/2015 | | 11/25/2015 | | DONE |
Kristal Soland
|
|
|
|
Sprinkler Plan Check | 11/23/2015 | | 11/23/2015 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
Miscellaneous action | | | 11/23/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 11/19/2015 | | 11/19/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/19/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 10/26/2015 | | 10/26/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/26/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/26/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 10/23/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/23/2015 | | 10/23/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 12 2015 8:26AM
|