INSP-Final Inspection | 2/15/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 2/15/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2016 | 2/12/2016 | 2/12/2016 | A | FAIL |
Troy Cobbley
|
|
|
Started test but the fitter found a leak at a 90.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2016 | 2/11/2016 | 2/11/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Sprinkler Rough-in | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed and piping can be covered.
|
INSP-Sprinkler Rough-in | 11/25/2015 | 11/30/2015 | 11/30/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground supply is ok to cover
|
INSP-Sprinkler Rough-in | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | FAIL |
Troy Cobbley
|
|
|
Pipe is not at the minimum 4'-6" bury
|
Permit Ready to Issue | | | 10/21/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/21/2015 | | 10/21/2015 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 10/20/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/20/2015 | | 10/20/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/20/2015 | | 10/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/20/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 12 2015 1:45PM
|