INSP-Final Inspection | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 1/26/2016 | 1/27/2016 | 1/27/2016 | A | CANC |
Katie Marron
|
|
|
Sprinkler head was not replaced at 3pm. Deferred to final.
|
INSP-Sprinkler Rough-in | 1/26/2016 | 1/27/2016 | 1/27/2016 | A | PASS |
Troy Cobbley
|
|
|
One wrong pendant has been installed. Will be verifed that its changed out at final.
|
INSP-Sprinkler Rough-in | 12/15/2015 | 12/15/2015 | 12/15/2015 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for the hard lids complete, approved for cover. Stairs will be added at a later date with heads installed under the stairs, contractor will call for inspection when complete.
|
Sprinkler Plan Check | 10/21/2015 | | 10/21/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/21/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/21/2015 | | 10/21/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 10/20/2015 | | 10/20/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/20/2015 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 10/19/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 19 2015 1:45PM
|