Case Summary | | | 12/8/2015 | | DONE |
|
|
|
|
INSP-Final Inspection | 11/20/2015 | 11/23/2015 | 11/23/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 11/20/2015 | | DONE |
|
|
|
Resubmitted drawings don't have a scaled graph. I emailed Matt Casey to request he email me a revised drawing that includes this. A new drawing was received and uploaded.
|
Alarm Plan Check | 11/20/2015 | | 11/20/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/20/2015 | | DONE |
|
|
|
Resubmittal approved with review comments.
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/20/2015 | | 11/20/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Plan resubmittals received | | | 11/19/2015 | | DONE |
|
|
|
Corrected drawings uploaded.
|
Miscellaneous action | | | 10/29/2015 | | DONE |
|
|
|
Received an email from the system designer that indicated the PDS interperetation of code was not correct regarding the requirement of an emergency voice communication system. He feels that this code only applies to high rise buildings, based on his review of the 2006 IBC and 2003 IFC. I informed him that we reviewed design based on 2012 and that this version requires the voice system. He wanted to substitued horn strobe notification. I informed him that the architect's design and building code reviewers comments required the voice system and the horn strobe substitution would not be allowed, since it does not meet minimum code requirements.
|
Miscellaneous action | | | 10/29/2015 | | DONE |
|
|
|
Via email, the designer conceided to the code requirements and will provide a voice system.
|
Miscellaneous action | | | 10/28/2015 | | DONE |
|
|
|
Checklist received
|
1st review completed | | | 10/28/2015 | | FAIL |
|
|
|
Emergency voice alarm system required. See review comments.
|
Miscellaneous action | | | 10/28/2015 | | DONE |
|
|
|
Emailed 1st review comments to Matt Casey and discussed deficiencies on the phone with him.
|
Plan assigned to (Lee) | 10/23/2015 | | 10/23/2015 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 10/23/2015 | | DONE |
|
|
|
Emailed Matt Casey to request the #601 checklist that was not included in the submittal.
|
Application received | | | 10/20/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 20 2015 11:59PM
|