INSP-Final Inspection | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Sprinkler Rough-in | 5/24/2016 | 5/24/2016 | 5/24/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, piping that is not exposed to attic spaces approved for cover. Fire sprinkler piping located in attic spaces cannot be covered until tenting inspection is performed and approved.
|
INSP-Sprinkler Rough-in | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Jim Page
|
|
|
Previously noted tenting/insulation items repaired, all of third level approved for cover.
|
INSP-Sprinkler Rough-in | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | FAIL |
Jim Page
|
|
|
3rd level piping not approved for cover, some area's have exposed piping in the attic area with no insulation tenting cover. Main fire sprinkler feed for the third level is wrapped with insulation, piping needs to have clear pocket between sheetrock and piping to help prevent freezing. Notified general contractor of issues, 3rd level east side will need to be inspected again to verify corrections before cover can be approved.
|
INSP-Sprinkler Rough-in | 3/9/2016 | 3/10/2016 | 3/10/2016 | P | PART |
Jim Page
|
|
|
Tenting inspection complete for the west side of the fire doors located on the third level. Overhead fire sprinkler piping on west side of 3rd level fire doors approved for cover, east side still needs tenting insulation installed and inspection performed. Third level, east side of fire doors cannot be covered until inspection of tenting is completed.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/25/2016 | 2/25/2016 | P | PASS |
Jim Page
|
|
|
Overhead fire sprinker hydrostatic test passed/complete for 1st floor, 2nd floor and 3rd floor. All hydrostatic tests complete for building A-2.
|
INSP-Sprinkler Rough-in | 2/17/2016 | 2/19/2016 | 2/19/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for 1st and 2nd level, building A-2, overhead fire sprinkler piping approved for cover. Third level rough to cover inspection performed, inspection passed for rough-in, piping on third level cannot be covered until tenting/insulation inspection is completed.
|
Sprinkler Plan Check | 10/30/2015 | | 10/30/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/30/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/30/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/30/2015 | | 10/30/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 10/29/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/29/2015 | | 10/29/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/22/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2015 5:36PM
|