INSP-Final Inspection | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | PASS |
Jim Page
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Jim Page
|
|
|
Final Fire Alarm inspection complete
|
INSP-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Scott Arellano
|
|
|
Completed fire alarm inspeciton of commercial kitchen area and associated exit passageway. Completed testing and inspection of exterior passageway protection; per engineered fire alarm drawings withing electrical plan sheets under FIR16-00128.
|
INSP-Final Inspection | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | PART |
Jim Page
|
|
|
Partial final fire alarm inspection for the district side of the convention center complete. Items still needing to be inspected is the kitchen area of level 1. Area labeled as level 5, level 4 , level 3 parking, level 2 parking, level 2 and level 1 lobby area complete for audio/visual notification on fire alarm system.
|
INSP-Final Inspection | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PART |
Jim Page
|
|
|
Partial final inspection complete for core and shell audio visual devices associated with this permit, A/V's on floors 1 through 9 associated with core and shell complete, door holders on floors 5, 6, 7, and 8 have been tested and work correctly, flow switches and tampers on the fire sprinklers floor 1 through 9 have been completed.
|
INSP-Sprinkler Rough-in/Hydro | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | CANC |
Jim Page
|
|
|
Inspection request for alarm final, not for sprinklers, inspection request cancelled and a new inspection request will be generated.
|
INSP-Conference | 7/29/2016 | 8/1/2016 | 8/1/2016 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
INSP-Conference | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | DONE |
Jim Page
|
|
|
Fire alarm conference complete, tested smoke detectors associated with shell and core on levels 1 through 9, tested audio visual devices associated with shell and core on floors 1 through 9, tested loss of battery power trouble at main panel.
|
INSP-Conference | 7/11/2016 | 7/12/2016 | 7/12/2016 | A | DONE |
Jim Page
|
|
|
Conference complete, tested flow switches and valve tamper switches for levels 1 throught 9 and wet pipe sprinkler systems, all tested satisfactorily.
|
INSP-Conference | 7/6/2016 | 7/8/2016 | 7/8/2016 | A | CANC |
Jim Page
|
|
|
Conference request cancelled per conversation with Ken, Phone #: ###-####.
|
Miscellaneous action | | | 7/8/2016 | | DONE |
|
|
|
Emailed Ken to let him know that Shilo installed sprinkler heads in all elevator pits and that he is to install required smoke detection. I suggested he contact the state elevator inspector's office to see if having a motor located in a sprinlered pit would require shunt trip functions.
|
Meeting | | | 7/7/2016 | | DONE |
|
|
|
Met with Ken and Rita regarding elevator machine room-less controlers and associated detection. I informed Ken that smoke detection will be required within the shaft if any motors or controls are located there as well. If the controller is wall mounted outside of the shaft, detection will be required within the enclosure. If space is not available, detector is to be mounted outside of the enclosure within the allowed spacing of the detector just like elevator lobby detectors. Subsequent to the meeting, I called Gary Barnes - state elevator supervisor. He confirmed that when controls or motors are located within the shaft, the shaft becomes the control space and requires detection mounted at the top.
|
Telephone call | | | 7/6/2016 | | DONE |
|
|
|
Ken called to say there were some changes that the mechanical engineer of record was making that would affect smoke damper coverage and he wanted clarification of detection requirements. I emailed him the details of IMC 607.3.3.2 - 607.4 requirements.
|
Miscellaneous action | | | 7/1/2016 | | DONE |
|
|
|
Emailed Ken to let him know that during a walk through, we noticed fire alarm plenum wire tied directly to all thread at the transition area of 4th floor from city center to the district. Told him that he needs to have the electricians correct this, as it is not allowed as proper installation by NFPA 70 (NEC). Also informed him that the Clearwater basketball backboards are blocking the strobes when in the up position. These need to be relocated clear of the backboards and maintain approved spacing for the selected candela.
|
Telephone call | | | 6/15/2016 | | DONE |
|
|
|
Ken called to say that he has found that return air systems do not exist in the mechanical system and is requesting that duct smoke detector be eliminated. I informed him that if they are not required, they do not have to be put in.
|
Telephone call | | | 2/24/2016 | | DONE |
|
|
|
Ken called to discuss seperating the project into 2 permits. 1 for VRT and 1 for the shell & Core. I told him I agreed. He will submit seperated drawings for VRT in the near future.
|
Alarm Plan Check | 1/21/2016 | | 1/21/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/21/2016 | | PASS |
|
|
|
Third resubmittal approved with review comments and requirements as noted.
|
Permit Ready to Issue | | | 1/21/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/21/2016 | | 1/21/2016 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 1/19/2016 | | DONE |
|
|
|
Emailed Ken to inform him that there are corrections that need to be made on floor plans 7 & 8. Floor 7 was identical to floor 6 and floor 8 was showing information for floor 7. Corrected drawings were received 1/20/16.
|
Plan resubmittals received | | | 1/15/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/29/2015 | | DONE |
|
|
|
Returned Ken's call to discuss strobe spacing requirement of floor 5 mezzanine and smoke control requirements. It was agreed that the strobe coverage would be corrected and that smoke control for stairwelsls and corridor 119 will be designed and installed in accordance with 2012 IFC 909.16, as noted in the fire code review and fire alarm plan reviews.
|
Plan resubmittals received | | | 12/28/2015 | | DONE |
|
|
|
Resubmittals received 12-24-2015
|
Miscellaneous action | | | 12/28/2015 | | DONE |
|
|
|
3rd review comments emailed to Ken. Outstanding items include visual notification coverage for floor 5 and manual / automatic smoke control with fan status.
|
Alarm Plan Check | 12/17/2015 | | 12/17/2015 | | FAIL |
Lee G Meredith
|
|
|
Resubmittal review failed due to numerous items. See 2nd review comments dated 12-17-2015.
|
Miscellaneous action | | | 12/17/2015 | | DONE |
|
|
|
2nd review comments emailed to Ken Webster.
|
Miscellaneous action | | | 12/16/2015 | | |
|
|
|
Corrected drawings received with room names.
|
Miscellaneous action | | | 12/15/2015 | | DONE |
|
|
|
Room names missing on 4 drawings that previously had them. I emailed Rita to request she make corrections and email them to me. Informed her that review cna't continue until they are received.
|
Plan resubmittals received | | | 12/14/2015 | | DONE |
|
|
|
|
Telephone call | | | 11/20/2015 | | DONE |
|
|
|
Ken called to say again that he didn not intend to provide smoke control features through the fire alarm system. He said this will be provided by the mechanical contractor. He called later to indicate that he would be providing smoke control through the fire alarm panel.
|
Miscellaneous action | | | 11/5/2015 | | DONE |
|
|
|
Ken Webster emailed to indicate that Shilo says there is no heat trace on this project. Tim Frost had confused this project with Simplot Headquarters and misinformed me. I let ken know that heat trace monitoring will not be required at this location, considering the current design.
|
Telephone call | | | 11/3/2015 | | DONE |
|
|
|
Ken called to discuss review comments. He is in the process of making corrections. He indicated that he will not be providing pressurization fan control, as noted in the review. He will pass this back to the general contractor.
|
1st review completed | | | 10/30/2015 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 10/29/2015 | | DONE |
|
|
|
Email to mechanical engineer to clarify mechanical design with regards to fire alarm system interface for fan control.
|
Plan assigned to (Lee) | 10/26/2015 | | 10/26/2015 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 10/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 25 2015 8:01PM
|