Miscellaneous action | | | 10/18/2016 | | DONE |
|
|
|
As built drawings received electronically.
|
INSP-Final Inspection | 9/20/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete.
|
INSP-Final Inspection | 9/15/2016 | 9/20/2016 | 9/20/2016 | A | CANC |
Jim Page
|
|
|
Inspection request was moved to this afternoon, due to scheduling issues for this afternoon this inspection request is cancelled and will be rescheduled for 10am on 21SEPT2016.
|
INSP-Alarm Testing | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | DONE |
Jim Page
|
|
|
Alarm testing complete, all devices with the new fire alarm system has been tested. A 10% functionality test will be performed on the new fire alarm system after the old fire alarm system and components have been removed. Note that the 5th floor pre-action isolation valve has a visible leak on the valve (leaks in the fire sprinkler system has the potential to cause false alarms), leak needs to be repaired before fire alarm system will by signed off as complete,
|
INSP-Final Inspection | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PART |
Jim Page
|
|
|
Tested smokes and A/V's on level 7, level 6, level 5 and level 4, all devices tested properly. Tested elevator recall as well as elevator shunt trip, devices tested corectly. Tested HVAC unit shutdown for in-duct smoke detectors on level 2, all tested correctly. Items left to inspect, associated devices with fire sprinkler system and VESDA systems.
|
INSP-Final Inspection | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PART |
Jim Page
|
|
|
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected level 3 smoke detectors and pull stations, remaining detection on level 3 is VESDA systems which will be tested at a later date. Level 1 smoke detectors/duct detectors/pull stations spot checked, devices tested operated correctly. Level 1 inspection complete, partial completion for level 3, contractor will schedule inspection request when other area's are ready.
|
INSP-Final Inspection | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | PART |
Jim Page
|
|
|
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected basement level alarm system install with device testing, basement level inspection is passed/complete, contractor will schedule remaining floors for later date.
|
INSP-Conference | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | DONE |
Jim Page
|
|
|
Fire alarm conference complete.
|
Miscellaneous action | | | 12/18/2015 | | DONE |
|
|
|
Upon further review, pull stations will be required in all locations per 2012 IFC 907.2.2 exception. Charlie emailed to indicate that the building is not sprinklered throughout, which is a requirement of the exception.
|
Miscellaneous action | | | 12/8/2015 | | DONE |
|
|
|
Dante emailed to note the engineer wants to remove all pull stations except for one that will be located at the command center. I replied to say that this was acceptable.
|
Issue and Print Permit | | | 12/7/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/7/2015 | | 12/7/2015 | | DONE |
Brittany Hill
|
|
|
|
Alarm Plan Check | 12/1/2015 | | 12/1/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/1/2015 | | DONE |
|
|
|
Plans approved with review comments. 12-1-15 pdf
|
1st review completed | | | 11/23/2015 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 11/18/2015 | | DONE |
|
|
|
Revised drawings received. Some non required devices were removed from the design.
|
Miscellaneous action | | | 11/13/2015 | | DONE |
|
|
|
Simplex is reviewing and redesigning, based on site review. New drawings will be submitted.
|
Miscellaneous action | | | 11/2/2015 | | DONE |
|
|
|
Per Charlie Bayne, submitted drawings are preliminary. A pre-construction site visit is scheduled on 11/6/15 to review actural requirements. Charlie has indicated that the engineer of record has provided a design that exceeds code in some ways but may not meet code in other ways. Site review is to determine actual requirements prior to start of installation.
|
Application received | | | 10/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 30 2015 12:13PM
|