Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR15-00767
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 619 W BANNOCK ST
Project NameAT&T Fire Alarm Replacement
Customer Number 
ePlanReviewYes
Description
AT&T FA Replacement work is the replacement of building fire alarm/detection system (less air sampling systems - to remain) with new addressable system. New system will also monitor all fire protection devices including pumps, flow switches, valves equipped with tamper switch, etc.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  10/18/2016 DONE
As built drawings received electronically.
INSP-Final Inspection9/20/20169/21/20169/21/2016APASS
DetailsJim Page
Final fire alarm inspection passed/complete.
INSP-Final Inspection9/15/20169/20/20169/20/2016ACANC
DetailsJim Page
Inspection request was moved to this afternoon, due to scheduling issues for this afternoon this inspection request is cancelled and will be rescheduled for 10am on 21SEPT2016.
INSP-Alarm Testing6/22/20166/23/20166/23/2016ADONE
DetailsJim Page
Alarm testing complete, all devices with the new fire alarm system has been tested. A 10% functionality test will be performed on the new fire alarm system after the old fire alarm system and components have been removed. Note that the 5th floor pre-action isolation valve has a visible leak on the valve (leaks in the fire sprinkler system has the potential to cause false alarms), leak needs to be repaired before fire alarm system will by signed off as complete,
INSP-Final Inspection6/14/20166/15/20166/15/2016APART
DetailsJim Page
Tested smokes and A/V's on level 7, level 6, level 5 and level 4, all devices tested properly. Tested elevator recall as well as elevator shunt trip, devices tested corectly. Tested HVAC unit shutdown for in-duct smoke detectors on level 2, all tested correctly. Items left to inspect, associated devices with fire sprinkler system and VESDA systems.
INSP-Final Inspection5/10/20165/11/20165/11/2016APART
DetailsJim Page
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected level 3 smoke detectors and pull stations, remaining detection on level 3 is VESDA systems which will be tested at a later date. Level 1 smoke detectors/duct detectors/pull stations spot checked, devices tested operated correctly. Level 1 inspection complete, partial completion for level 3, contractor will schedule inspection request when other area's are ready.
INSP-Final Inspection3/8/20163/9/20163/9/2016APART
DetailsJim Page
Project is being worked in phases, contractor is going floor by floor for partial inspection and a final alarm inspection for entire building at project completion. Inspected basement level alarm system install with device testing, basement level inspection is passed/complete, contractor will schedule remaining floors for later date.
INSP-Conference1/5/20161/6/20161/6/2016ADONE
DetailsJim Page
Fire alarm conference complete.
Miscellaneous action  12/18/2015 DONE
Upon further review, pull stations will be required in all locations per 2012 IFC 907.2.2 exception. Charlie emailed to indicate that the building is not sprinklered throughout, which is a requirement of the exception.
Miscellaneous action  12/8/2015 DONE
Dante emailed to note the engineer wants to remove all pull stations except for one that will be located at the command center. I replied to say that this was acceptable.
Issue and Print Permit  12/7/2015 DONE
Inspection Record Card- Fire12/7/2015 12/7/2015 DONE
DetailsBrittany Hill
Alarm Plan Check12/1/2015 12/1/2015 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  12/1/2015 DONE
Plans approved with review comments. 12-1-15 pdf
1st review completed  11/23/2015 FAIL
See 1st review comments.
Miscellaneous action  11/18/2015 DONE
Revised drawings received. Some non required devices were removed from the design.
Miscellaneous action  11/13/2015 DONE
Simplex is reviewing and redesigning, based on site review. New drawings will be submitted.
Miscellaneous action  11/2/2015 DONE
Per Charlie Bayne, submitted drawings are preliminary. A pre-construction site visit is scheduled on 11/6/15 to review actural requirements. Charlie has indicated that the engineer of record has provided a design that exceeds code in some ways but may not meet code in other ways. Site review is to determine actual requirements prior to start of installation.
Application received  10/30/2015 DONE
Application submitted via PDS Online on Oct 30 2015 12:13PM