INSP-Final Inspection | 2/26/2016 | 2/26/2016 | 2/26/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete, notated areas with red ink on city approved drawings, all area's approved for cover.
|
INSP-Sprinkler Rough-in | 1/7/2016 | 1/8/2016 | 1/8/2016 | A | PASS |
Troy Cobbley
|
|
|
see the city approved plans for piping abobe hard lib is ok for cover.
|
Intake Approval | | | 11/3/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/3/2015 | | 11/3/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/3/2015 | | 11/3/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/3/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/3/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/3/2015 | | 11/3/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 10/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 30 2015 1:32PM
|