INSP-Final Inspection | 2/17/2016 | 2/18/2016 | 2/18/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Supply line flush | 2/16/2016 | 2/17/2016 | 2/17/2016 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Final Inspection | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | FAIL |
Katie Marron
|
|
|
Inspection was not a final. It was hydro test for the underground. System dropped to 172 psi from 200 psi, failed. System to be retested.
|
INSP-Sprinkler Rough-in | 12/30/2015 | 12/31/2015 | 12/31/2015 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground piping passed/complete, approved for cover. Hydrostatic 2 hour @ 200psi test passeed/complete.
|
Permit Ready to Issue | | | 11/23/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/23/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/23/2015 | | 11/23/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 11/12/2015 | | 11/12/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/12/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2015 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 11/10/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/10/2015 | | 11/10/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/3/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 3 2015 10:11AM
|