INSP-Final Inspection | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Underground final inspection complete
|
INSP-Sprinkler Rough-in/Hydro | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Underground hydrostatic complete
|
INSP-Sprinkler Rough-in | 3/1/2016 | 3/1/2016 | 3/1/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection performed on 18NOV2015 for underground piping, underground was approved for cover at that inspection.
|
INSP-Supply line flush | 2/28/2016 | 2/29/2016 | 2/29/2016 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2016 | 2/29/2016 | 2/29/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test, 2 hours @ 200 psi complete for underground supply.
|
INSP-Supply line flush | 2/24/2016 | 2/26/2016 | 2/26/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Robert, phone number ###-####, will reschedule for later date.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/26/2016 | 2/26/2016 | A | PASS |
Jim Page
|
|
|
Underground main supply hydrostatic test complete.
|
Intake Approval | | | 11/6/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/6/2015 | | 11/6/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/6/2015 | | 11/6/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/6/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/6/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 11/6/2015 | | DONE |
|
|
|
|
Application received | | | 11/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 4 2015 3:10PM
|