INSP-Final Inspection | 7/28/2016 | 7/29/2016 | 7/29/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete. Contractor will be hanging headbox in riser room as well as signage for fire sprinkler riser door. Items will be verified at final life fire safety inspection.
|
INSP-Final Inspection | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | CANC |
Jim Page
|
|
|
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final Inspection | 7/20/2016 | 7/22/2016 | 7/21/2016 | A | CANC |
Jim Page
|
|
|
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 4/12/2016 | 4/13/2016 | 4/13/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for tenting complete, all fire sprinkler piping in this building approved for cover.
|
INSP-Supply line flush | 3/1/2016 | 3/4/2016 | 3/4/2016 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
|
INSP-Sprinkler Rough-in | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for 1st level, all of 1st level approved for cover. Contractor will schedule inspection for 2nd level when tenting is complete.
|
INSP-Sprinkler Rough-in | 2/29/2016 | 3/1/2016 | 3/1/2016 | P | FAIL |
Jim Page
|
|
|
Rough to cover inspection performed, cover is not approved, numorous hangers are overspaced, hanger spacing needs to be corrected throughout entire building before cover is approved.
|
INSP-Sprinkler Rough-in/Hydro | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | FAIL |
Jim Page
|
|
|
Rough to cover inspection performed, cover is not approved, inspection stopped after finding numorous hangers that are overspaced, hanger spacing needs to be corrected throughout entire building before cover is approved.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Jim Page
|
|
|
Overhead hydrostatic test, 2 hours @ 200psi passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2016 | 2/26/2016 | 2/26/2016 | P | CANC |
Jim Page
|
|
|
Please call Anthony before you head out! Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Supply line flush | 12/17/2015 | 12/17/2015 | 12/17/2015 | P | PASS |
Jim Page
|
|
|
Inspection request was for an underground hydrostatic test, 2 hours @ 200 psi hydrostatic test for underground passed/complete. Main line supply still needs flushed.
|
INSP-Supply line flush | 12/16/2015 | 12/17/2015 | 12/17/2015 | A | CANC |
Jim Page
|
|
|
Underground hydro. Call Jake when heading out! Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
Permit Ready to Issue | | | 12/3/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/3/2015 | | 12/3/2015 | | DONE |
Kristal Soland
|
|
|
|
Sprinkler Plan Check | 11/20/2015 | | 11/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 11/20/2015 | | FAIL |
Tim Frost
|
|
|
|
Intake Approval | | | 11/9/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/9/2015 | | 11/9/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/6/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2015 1:28PM
|