INSP-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Stan Beus
|
Permit Ready to Issue | | | 7/23/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/23/2018 | | DONE |
|
|
|
|
INSP-Final Inspection | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | FAIL |
Troy Cobbley
|
|
|
I need to verify as-builts match installation, both vents on the fire pump fuel tank need to vent to the exterior of the building as per NFPA 20 and IFC requirements.
Mike Martin is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/16/2018 | 7/20/2018 | 7/20/2018 | A | FAIL |
Troy Cobbley
|
|
|
Pump commissioning passed. Need as-builts of the fire pump assembly as discussed, need approval from the fire dept on the fuel tank venting. Need signage on the fire pump room door. Need all of the fire alarm interconnections tested.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 7/20/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 7/20/2018 | | 7/20/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/20/2018 | | 7/20/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2018 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test for the fire pump piping passed.
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Troy Cobbley
|
|
|
Most corrections have been made and are marked "ok" on the plans. Still need earthquaking at the 6" existing riser and at the risers in the fire pump room.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was for the bulk mains. Missing branchline restraints, missing heads in Fire Pump Room, missing earthquake bracing, missing clearance at CMU walls.
Tile can be installed in Service Bay but will need to be left out at the earthquake bracing locations.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan Modification Accepted | | | 8/25/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 8/25/2017 | | 8/25/2017 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/25/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/25/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/25/2017 | | DONE |
Christina Prado
|
|
|
|
Plan Modification Accepted | | | 8/17/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/17/2017 | | 8/17/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/17/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
INSP-Conference | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | DONE |
Troy Cobbley
|
|
|
Per Assistant Chief Ron Johnson the Temporary Occupancy is to continue until directed otherwise. Included is the email dated 8/15/16 giving current status.
From: Ronald Johnson Sent: Monday, August 15, 2016 10:04 AM To: Quinton Boyer Cc: Tom Easton ; Randy Bowron ; Mike Bierman ; Tim Frost ; Scott Arellano ; Romeo Gervais Subject: Fire Flow for Larry Miller Subaru
Mr. Boyer,
I met Suez Water field techs last week to witness a flow test at the fire hydrant at the northwest corner of Larry Miller Subaru. The results of the flow test are as follows.
Outlet: 4.5”, Discharge Coefficient .9
Static: 57
Pitot: 26
Residual: 45
Actual Flow: 2772 gpm
Flow at 20psi: 5092 gpm
The available fire flow as calculated using the flow test does not support a properly functioning fire sprinkler system as designed. I discussed these results with Suez and inquired if there would be any stability increase in the system in the near future. There are no plans for any improvements that would stabilize or increase the pressure in this area in the foreseeable future. Unfortunately, the sprinkler system for Larry Miller Subaru was designed using a fire flow that does not reflect the significant daily drop in pressure. This daily drop in pressure lasts several hours and is expected to occur at least 3.5 to 4 months of the year. If a fire were to occur in the building, the sprinkler system may not be sufficient to keep it in check or extinguish the fire during several hours of the day. I know this is very inconvenient and will likely be expensive to resolve, so I am open to a reasonable timeline for repairs. Please respond with a plan and proposed timeline. I am willing to discuss this and answer questions you and the owner may have by phone or in person. Would you mind forwarding owner contact information to me so I can contact them?
Regards,
cid:image001.jpg@01CE20C9.F3E72450 Ron Johnson
Division Chief – Assistant Fire Marshal
|
INSP-Conference | 7/8/2016 | 7/8/2016 | 7/8/2016 | A | CANC |
Troy Cobbley
|
|
|
60 psi on the guage this morning
|
INSP-Conference | 7/6/2016 | 7/7/2016 | 7/7/2016 | A | DONE |
Troy Cobbley
|
|
|
Pressure was 64psi this morning
|
INSP-Conference | 7/6/2016 | 7/6/2016 | 7/6/2016 | A | DONE |
Troy Cobbley
|
|
|
Pressure was 62psi this morning
|
INSP-Conference | 7/5/2016 | 7/5/2016 | 7/5/2016 | A | DONE |
Troy Cobbley
|
|
|
Reading on the guage this morning was 70psi
|
INSP-Conference | 7/1/2016 | 7/1/2016 | 7/1/2016 | A | DONE |
Troy Cobbley
|
|
|
57psi on the guage this morning
|
INSP-Conference | 6/30/2016 | 6/30/2016 | 6/30/2016 | A | DONE |
Troy Cobbley
|
|
|
Pressure this morning was 69psi
|
INSP-Conference | 6/29/2016 | 6/29/2016 | 6/29/2016 | A | DONE |
Troy Cobbley
|
|
|
57psi on the guage at 7:00 am this morning
|
INSP-Conference | 6/28/2016 | 6/28/2016 | 6/28/2016 | A | PASS |
Troy Cobbley
|
|
|
I witnessed 64psi at the base of riser.
|
INSP-Conference | 6/28/2016 | 6/28/2016 | 6/28/2016 | A | DONE |
Troy Cobbley
|
|
|
This inspection actually occured on 6/27/16 where I witnessed pressure at the base of riser at 59psi
|
INSP-Final Inspection | 6/8/2016 | 6/8/2016 | 6/8/2016 | A | PART |
Troy Cobbley
|
|
|
Per the Fire Marshal, a TCO can be issued for the building permit (BLD15-01869) for the next 30 days. The static pressure at the base of the fire riser will need to be monitored and recorded over the next 30 days by the general contractor. These readings will be evaluated by the Fire Marshal at the end of the 30 days to determine if fire sprinkler system design changes will be necessary under (FIR15-00822) to accommodate the actual water supply available onsite.
|
INSP-Final Inspection | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | PART |
Troy Cobbley
|
|
|
I stopped at the project site three times today to verify static pressure on the underground supply line. At 7:00am the pressure was at 61psi, at 9:00am the pressure was at 71psi and at 1:00pm the pressure was at 74 psi. I contacted the project superintendant and the fire sprinkler contractor and let them know that I could not sign off until directed by my supervisor.
Mike is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Meeting | | | 6/7/2016 | | DONE |
Scott Arellano
|
|
|
Per the Fire Marshal, a TCO can be issued for the building permit (BLD15-01869) for the next 30 days. The static pressure at the base of the fire riser will need to be monitored and recorded over the next 30 days by the general contractor. These readings will be evaluated by the Fire Marshal at the end of the 30 days to determine if fire sprinkler system design changes will be necessary under (FIR15-00822) to accommodate the actual water supply available onsite.
|
INSP-Conference | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | DONE |
Troy Cobbley
|
|
|
“Met Mike Bierman onsite to evaluate pressure at base of riser assembly. Pressure gauge indicated 73psi on one riser gauge and 78 psi on the other riser pressure gauge. We agreed to check the pressure once again the following morning to verify that the minimum require base of riser (BOR) pressure is accurate per system design. Final sign off can occur with this follow up pending verification.”
|
INSP-Final Inspection | 6/2/2016 | 6/3/2016 | 6/3/2016 | A | CANC |
Troy Cobbley
|
|
|
Shilo has provided info on corrected gpm requirements that will need to be approved by Tim Frost for the forward flush
|
INSP-Final Inspection | 5/27/2016 | 5/31/2016 | 5/31/2016 | A | FAIL |
Troy Cobbley
|
|
|
Forward flow test passed with a temporary outlet to the exterior but it needs to be permanent as per discussion. Pressure at riser indicated 56psi. Plans and calculations submitted require a minimum of 75psi at base of riser.
|
INSP-Final Inspection | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | FAIL |
Troy Cobbley
|
|
|
The interconnects with the fire alarm system tested ok. Forward flush failed.
|
INSP-Final Inspection | 5/23/2016 | 5/24/2016 | 5/24/2016 | P | CANC |
Troy Cobbley
|
|
|
Mark is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | CANC |
Troy Cobbley
|
|
|
Mark Jensen is the contact - ###-#### - would like a Hydro test this afternoon. Thank you Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | PASS |
Troy Cobbley
|
|
|
Remaining piping is ok to cover. Missing one pendant in the west service bay.
|
INSP-Sprinkler Rough-in | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas where piping can be covered. I noted pendants are overspaced in the Electrical Room.
|
INSP-Sprinkler Rough-in | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new area where the piping is ok to cover clouded and marked with todays date.
|
INSP-Sprinkler Rough-in | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the ShowRoom area where piping has been clouded in red that is ok to cover.
|
INSP-Sprinkler Rough-in | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping marked "ok" whre piping above hard lids can be covered.
|
Miscellaneous action | | | 4/5/2016 | | PASS |
|
|
|
I have review the new as built changes for this project. The hydraulics are close to the minimum of 5% (5.8%) however, they are adequate and approved.
|
INSP-Sprinkler Rough-in | 3/28/2016 | 3/29/2016 | 3/29/2016 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered above the hardlids. Also plan modifications will again be required due to additional fittings and an elevation change that has not been included on the latest plans. The elevation change and the additional fittings will effect the hydraulic calculations and will need to be verified through the plan review process. Also at several locations where the piping passes through CMU walls and rises up through the floor the hole size is not large enough to meet NFPA 13. The holes will need to be larger or flexible couplings will need to be utilized as per NFPA 13. For the most part the sprinkler rough-in is passed except for the items noted above. I will need verification that the wood used in several locations is fire treaded or upright protection will be required.
|
Intake Approval | | | 3/28/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/28/2016 | | 3/28/2016 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/28/2016 | | DONE |
|
|
|
|
INSP-Supply line flush | 3/21/2016 | 3/23/2016 | 3/23/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/21/2016 | 3/22/2016 | 3/22/2016 | P | PART |
Troy Cobbley
|
|
|
Underground hydro test passed. Overhead rough-in failed due to the approved plans not matching the installation such as riser nipples installed where none are shown. Also missing branch line restraints. Plan modifications are required showing all piping changes and the additional fittings in the mains and branchlines.
|
Sprinkler Plan Check | 12/9/2015 | | 12/9/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/9/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/9/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/9/2015 | | 12/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 11/30/2015 | | 11/30/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/30/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/30/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 11/25/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/25/2015 | | 11/25/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 16 2015 1:45PM
|
INSP-Conference | 8/15/2016 | 8/15/2016 | | P | |
|
|
|
|