INSP-Final Inspection | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for level 6 passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for level 6, hydrostatic test complete for overhead fire sprinkler piping on level 6, tamper switch and flow switch satisfactorily tested for level 6.
|
INSP-Sprinkler Rough-in | 6/15/2016 | 6/15/2016 | 6/15/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping above gridded area's on level 6 complete, fire sprinkler above gridded area's approved for cover.
|
INSP-Sprinkler Rough-in | 6/6/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on 6th floor complete, 6th floor approved for cover.
|
INSP-Sprinkler Rough-in | 1/12/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Jim Page
|
|
|
Rough in inspection complete, notated with red ink on city approved drawings area's inspected
|
Sprinkler Plan Check | 11/24/2015 | | 11/24/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/24/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/24/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/24/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/24/2015 | | 11/24/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 11/23/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/23/2015 | | 11/23/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/22/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2015 1:51PM
|