INSP-Final Inspection | 6/15/2017 | 6/15/2017 | 6/15/2017 | A | PASS |
Jim Page
|
|
|
Final inspection for underground supply passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 5/25/2017 | 5/26/2017 | 5/26/2017 | A | PASS |
Jim Page
|
|
|
Underground re-hydro tested due to developed leak from seperate contractor impacting thrust block. Restraints have been installed to protect underground from seperation due to site work and underground re-hydro complete.
|
INSP-Sprinkler Rough-in | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | PART |
Jim Page
|
|
|
Underground In Building Riser/thrust block inspected, approved for cover, remainder of underground still needs installed, contractor will schedule rest of underground for later date when completed.
|
INSP-Sprinkler Rough-in | 12/31/2015 | 1/5/2016 | 1/5/2016 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Brian, phone number ###-####, inspection will be rescheduled.
|
Intake Approval | | | 12/1/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/1/2015 | | 12/1/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/1/2015 | | 12/1/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/1/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/1/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/1/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/1/2015 | | 12/1/2015 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 11/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 25 2015 10:38AM
|