INSP-Final Inspection | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/8/2016 | 8/9/2016 | 8/9/2016 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection wsa just to verify the forward flush which passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2016 | 4/8/2016 | 4/8/2016 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in | 2/18/2016 | 2/18/2016 | 2/18/2016 | P | PASS |
Troy Cobbley
|
|
|
insulation in attic space above main roof structure has been verified.
|
INSP-Sprinkler Rough-in | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed for what is shown on the plans. See plans for several locations where small corrections are required. Piping can not be covered until I have access into the the upper overbuild and the enclosed front canopy to perform inspection and speak to the plan reviewer.
|
Issue and Print Permit | | | 1/22/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/22/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/21/2016 | | 1/21/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/21/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/19/2016 | | 1/19/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/19/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 1/14/2016 | | 1/14/2016 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/11/2016 | | 1/11/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/11/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/11/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 1/8/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/8/2016 | | 1/8/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2015 4:01PM
|