Permit Information
Permit NumberFIR15-00892
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 8813 W ARDENE ST
Project NameLinh Thu'u Temple
Customer Number 
ePlanReviewYes
Description
[Linh Thu'u Temple]
The fire sprinkler scope of work consists of protecting a single level structure with above and below protection per NFPA 13, 2013. A new 6” x 295’± Ductile Iron underground service will supply a 2” backflow preventer and riser. The system is design as two 1 ¼” loops.

(LINH THU'U TEMPLE) ""PLAN MODIFICATION TO INSTALL SPRAY FOAM INSULATION ON THE UNDERSIDE OF THE ROOF SHEETING TO CREEATE A CONDITIONED ATTIC"" (ESRs ARE ATTACHED) For the construction of a new 4900 sq. ft. wood framed religious building with an associated residential unit (1740 sq. ft.) with work to include all related site work, utilities mechanical plumbing and electrical work per the approved plans and the attached engineering. This building is fully fire sprinklered because of the r occupancy. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/22/20168/23/20168/23/2016APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection8/8/20168/9/20168/9/2016PFAIL
DetailsTroy Cobbley
Todays inspection wsa just to verify the forward flush which passed.
INSP-Sprinkler Rough-in/Hydro4/7/20164/8/20164/8/2016APASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Sprinkler Rough-in2/18/20162/18/20162/18/2016PPASS
DetailsTroy Cobbley
insulation in attic space above main roof structure has been verified.
INSP-Sprinkler Rough-in2/4/20162/4/20162/4/2016PPART
DetailsTroy Cobbley
Rough-in passed for what is shown on the plans. See plans for several locations where small corrections are required. Piping can not be covered until I have access into the the upper overbuild and the enclosed front canopy to perform inspection and speak to the plan reviewer.
Issue and Print Permit  1/22/2016 DONE
(F) Reprint permit  1/22/2016 DONE
Sprinkler Plan Check1/21/2016 1/21/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  1/21/2016 DONE
DetailsTim Frost
Sprinkler Plan Check1/19/2016 1/19/2016 FAIL
DetailsTim Frost
Miscellaneous action  1/19/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Sprinkler Plan Check1/14/2016 1/14/2016 FAIL
DetailsTim Frost
Sprinkler Plan Check1/11/2016 1/11/2016 FAIL
DetailsTim Frost
1st review completed  1/11/2016 FAIL
DetailsTim Frost
Miscellaneous action  1/11/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  1/8/2016 PASS
Plan assigned to (Tim)1/8/2016 1/8/2016 DONE
DetailsTim Frost
Application received  12/17/2015 DONE
Application submitted via PDS Online on Dec 17 2015 4:01PM