INSP-Final Inspection | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Staff review | 1/26/2016 | 1/26/2016 | 1/26/2016 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/26/2016 | | DONE |
|
|
|
as per Tim Frost; no fees due (see attached)
|
CHANGE STATUS TO (ISS) | | | 1/26/2016 | | DONE |
|
|
|
no fees due as per Tim Frost (see attachement)
|
Plan Modification Accepted | | | 1/26/2016 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 1/26/2016 | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. Plans/as-builts need submitted showing the reduced scope of work.
|
Permit Ready to Issue | | | 12/28/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/28/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/28/2015 | | 12/28/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/22/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/22/2015 | | 12/22/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/22/2015 | | 12/22/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/22/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2015 11:18AM
|