INSP-Final Inspection | 3/14/2016 | 3/15/2016 | 3/15/2016 | P | PASS |
Jim Page
|
|
|
Phase 1 final fire sprinkler inspection passed/complete
|
INSP-Alarm Testing | 3/14/2016 | 3/15/2016 | 3/15/2016 | P | DONE |
Jim Page
|
|
|
Alarm testing complete
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test (200 psi for 2 hours) complete for the four wet systems in the fire pump room. Rough in inspection complete for phase 1 fire sprinkler piping.
|
INSP-Sprinkler Rough-in | 3/7/2016 | 3/10/2016 | 3/10/2016 | A | DONE |
Jim Page
|
|
|
Fire pump flow/testing complete
|
INSP-Supply line flush | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
Jim Page
|
|
|
Underground fire line flush passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2016 | 2/10/2016 | 2/10/2016 | P | PASS |
Jim Page
|
|
|
Underground hydrostatic (200psi for 2 hours) test passed/complete.
|
INSP-Sprinkler Rough-in | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for the underground passed/complete, underground approved for cover.
|
INSP-Sprinkler Rough-in | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection performed for underground piping. Partial cover approved for east to west piping, still need thrust block on 90 going to building as well as thrust block for riser inside. Contractor will schedule inspection for the rest of underground when complete.
|
Sprinkler Plan Check | 1/8/2016 | | 1/8/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/8/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/8/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/8/2016 | | 1/8/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/5/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/5/2016 | | 1/5/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/31/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 31 2015 11:19AM
|