Miscellaneous action | | | 10/13/2016 | | DONE |
|
|
|
FPC said the two sprinklers were changed out. I told him the project would still required a reinspection. I also sent a copy of the email to the field inspector.
|
Miscellaneous action | | | 10/12/2016 | | DONE |
|
|
|
FPC responded and said he thought the project WAS finaled. I told him it was not and suggested he get with Troy.
|
Miscellaneous action | | | 10/10/2016 | | DONE |
|
|
|
Sent a letter requesting status to the fpc
|
INSP-Final Inspection | 4/8/2016 | 4/11/2016 | 4/11/2016 | A | FAIL |
Troy Cobbley
|
|
|
The two standard responce pendants have not been changed to quick responce. Ron is going to walk the project and make sure all is right.
|
INSP-Sprinkler Rough-in | 1/22/2016 | 1/25/2016 | 1/25/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. I noted two standard responce pendant heads that will need to be changed to quick responce prior to a final sign off.
|
INSP-Sprinkler Rough-in | 1/21/2016 | 1/22/2016 | 1/22/2016 | A | FAIL |
Troy Cobbley
|
|
|
No plans on site and the installing contractor is trying to get ahold of the permit holder for the drawings. No inspection was performed.
|
Intake Approval | | | 1/8/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/8/2016 | | 1/8/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/8/2016 | | 1/8/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/8/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/8/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/8/2016 | | 1/8/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 1/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 6 2016 8:48AM
|