INSP-Final Inspection | 3/14/2016 | 3/14/2016 | 3/14/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for area of work, overhead sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 2/15/2016 | 2/17/2016 | 2/16/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for hardlids, approved for cover on hardlids only
|
INSP-Sprinkler Rough-in | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | PART |
Jim Page
|
|
|
Tenant space is located on the 10th floor, not the 11th floor. Rough to cover inspection for conference room hard lid complete, conference room hard lid approved for cover.
|
Sprinkler Plan Check | 1/12/2016 | | 1/12/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/12/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/12/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/12/2016 | | 1/12/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/11/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/11/2016 | | 1/11/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/11/2016 | | 1/11/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/11/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/11/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 7 2016 2:28PM
|