INSP-Final Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | CANC |
Troy Cobbley
|
|
|
Need the mechanical room ceiling resolved prior to final sign off. I spoke to Brian about the situation.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in | 2/26/2016 | 2/26/2016 | 2/26/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. Need hydro test.
|
Intake Approval | | | 1/19/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/19/2016 | | 1/19/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/19/2016 | | 1/19/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/19/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/19/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/19/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/19/2016 | | 1/19/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 1/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 14 2016 9:13AM
|