INSP-Final Inspection | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2016 | 2/24/2016 | 2/24/2016 | P | PASS |
Troy Cobbley
|
|
|
All sprinkler work is complete except for the two tamper switches being connected to the facp
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2016 | 2/23/2016 | 2/23/2016 | P | PASS |
Troy Cobbley
|
|
|
Inspection was to verify the two dry sidewalls installed at the top of the exhaust duct
|
INSP-Sprinkler Rough-in | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | PASS |
Troy Cobbley
|
|
|
Piping above drop in ceiling can be covered.
|
INSP-Sprinkler Rough-in | 1/22/2016 | 1/22/2016 | 1/22/2016 | P | PASS |
Troy Cobbley
|
|
|
The piping above the restroom is ok to cover.
|
Sprinkler Plan Check | 1/20/2016 | | 1/20/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/20/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/20/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/20/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/20/2016 | | 1/20/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/19/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/19/2016 | | 1/19/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 1/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 14 2016 3:51PM
|