INSP-Final Inspection | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 3/22/2016 | 3/23/2016 | 3/23/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test (200psi for 2 hours) complete for 6th floor. Rough to cover inspection complete for 6th floor, entire area of work on 6th floor approved for cover.
|
INSP-Sprinkler Rough-in | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | PART |
Jim Page
|
|
|
Notated areas approved for cover with yellow high-lighter/red ink on city approved drawings. Area's inspected approved for cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/26/2016 | | 1/26/2016 | | DONE |
Brittany Hill
|
|
|
|
Sprinkler Plan Check | 1/26/2016 | | 1/26/2016 | | PASS |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/21/2016 | | 1/21/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/21/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/21/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 1/20/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/20/2016 | | 1/20/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 1/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2016 11:54AM
|