Permit Information
Permit NumberFIR16-00049
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7546 W STATE ST
Project NameNorth Pointe #4
Customer Number 
ePlanReviewYes
Description
[North Pointe Retail Building #4]
The fire sprinkler scope of work consists of providing shell an core protection based on OH2. The system is designed as a grid layout with 2 ½” x 2 ½” x 1 ¼” pipe sizes. The new 4”x190’± C-900 underground with fittings and thrust blocks supplies a 3” backflow preventer with 4” riser.

(NORTH POINTE RETAIL – BLDG #4 – Shell and Core) Permit is to construct a 6,288 square foot Retail / Office / Assembly Shell building. This building is constructed as a wood frame building and a concrete footing. Work includes: new foundation, new exterior walls, new mechanical, stubbing in plumbing into the building, site work, new wood frame exterior walls, new manufactured wood truss roof system, and new electrical (Exterior Lighting Approved). This building will be fully Fire Sprinklered with an approved Fire Alarm system. System shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: In accordance with Section C401.2 option #1 of the 2012 IECC; ANSI/ASHREA/IESNA 90.1 were used to show compliance with the Energy Code. The lighting installed within the tenant spaces shall also comply with ASHREA. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/13/20166/14/20166/14/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection6/13/20166/14/20166/13/2016ACANC
DetailsJim Page
Please call Jake when you are heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro5/5/20165/6/20165/6/2016APASS
DetailsJim Page
Overhead 200 psi hydrostatic test complete. Rough in inspection will be scheduled when seismic bracing/end of line restraints are complete.
INSP-Sprinkler Rough-in/Hydro5/4/20165/5/20165/5/2016PCANC
DetailsJim Page
Please call Jake on your way out! Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Supply line flush4/5/20164/6/20164/6/2016ADONE
DetailsJim Page
Underground main line flush complete
INSP-Sprinkler Rough-in/Hydro3/10/20163/10/20163/10/2016APASS
DetailsJim Page
Underground rough to cover inspection complete, underground supply approved for cover. Hydrostatic test (200psi for 2 hours)for underground passed/complete.
Permit Ready to Issue  2/29/2016 DONE
Issue and Print Permit  2/29/2016 DONE
Inspection Record Card- Fire2/29/2016 2/29/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check2/24/2016 2/24/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  2/24/2016 DONE
DetailsTim Frost
Plan assigned to (Tim)1/25/2016 1/25/2016 DONE
DetailsTim Frost
Intake Approval  1/25/2016  
Sprinkler Plan Check1/25/2016 1/25/2016 FAIL
DetailsTim Frost
1st review completed  1/25/2016 FAIL
DetailsTim Frost
Miscellaneous action  1/25/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  1/22/2016 DONE
Application submitted via PDS Online on Jan 22 2016 9:57AM